[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906587":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906587,586,1,"单选题","盖挖半逆作法及类似逆作法的区别在于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","构筑中间支撑柱及覆盖板过程",false,{"key":16,"text":17,"correct":14},"B","开挖及支撑安装过程",{"key":19,"text":20,"correct":14},"C","构筑侧墙、柱及楼板过程",{"key":22,"text":23,"correct":24},"D","顶板完成及恢复路面过程",true,"本题考查的是隧道工程施工技术。盖挖半逆作法类似逆作法，其区别仅在于顶板完成及恢复路面过程。 2020版教材P302-317",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]