[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906581,586,1,"单选题","用于正常通车线路上的桥梁工程的换梁方法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","顶推法施工",false,{"key":16,"text":17,"correct":14},"B","转体法施工",{"key":19,"text":20,"correct":14},"C","悬臂法施工",{"key":22,"text":23,"correct":24},"D","横移法施工",true,"横移施工是在拟待安置结构的位置旁预制该结构物，并横向移运该结构物，将它安置在规定的位置上。横向位移施工多用于正常通车线路上的桥梁工程的换粱。为了尽量减少交通的中断时间，可在原桥位旁预制并横移施工。 2020版教材P283-287",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]