[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906580,586,1,"单选题","石灰稳定土路拌法施工工艺流程（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","准备下承层→施工放样→洒水闷料→粉碎土或运送、摊铺集料→整平和轻压→摆放和摊铺石灰→加水并湿拌→拌和→整型→碾压→接缝处理→养生",false,{"key":16,"text":17,"correct":14},"B","准备下承层→施工放样→粉碎土或运送、摊铺集料→整平和轻压→洒水闷料→摆放和摊铺石灰→拌和→整型→加水并湿拌→接缝处理→碾压→养生",{"key":19,"text":20,"correct":14},"C","准备下承层→施工放样→洒水闷料→粉碎土或运送、摊铺集料→整平和轻压→拌和→摆放和摊铺石灰→加水并湿拌→碾压→整型→接缝处理→养生",{"key":22,"text":23,"correct":24},"D","准备下承层→施工放样→粉碎土或运送、摊铺集料→洒水闷料→整平和轻压→摆放和摊铺石灰→拌和→加水并湿拌→整型→碾压→接缝处理→养生",true,"石灰稳定土路拌法施工的工艺流程：准备下承层→施工放样→粉碎土或运送、摊铺集料→洒水闷料→整平和轻压→摆放和摊铺石灰→拌和→加水并湿拌→整形→碾压→接缝处理→养生。 2020版教材P265-279",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]