[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},906546,586,1,"单选题","钢筋混凝土预制桩锤击沉桩法施工，通常采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","轻锤低击的打桩方式",false,{"key":16,"text":17,"correct":18},"B","重锤低击的打桩方式",true,{"key":20,"text":21,"correct":14},"C","先四周后中间的打桩顺序",{"key":23,"text":24,"correct":14},"D","先打短柱后打长桩","2020版教材P188 钢筋混凝土预制桩锤击沉桩法施工中，宜选用“重锤低击”，即锤的重量大而落距小，这样，桩锤不易产生回跃，不致损坏桩头，且桩易打入土中，效率高。打桩时注意事项:打桩应避免自外向内，或从周边向中间进行。当桩基的设计标高不同时，打桩顺序宜先深后浅;当桩的规格不同时，打桩顺序宜先大后小、先长后短。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]