[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906516":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906516,586,1,"单选题","关于钢筋混凝土预制桩加工制作，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","长度在10m以上的桩必须工厂预制",false,{"key":16,"text":17,"correct":14},"B","重叠法预制不宜超过6层",{"key":19,"text":20,"correct":21},"C","桩的强度达到设计强度的100％方可运输和打桩",true,{"key":23,"text":24,"correct":14},"D","重叠法预制下层桩强度达到设计强度70％时方可灌注上层桩","2020版教材P187 本题考查的是地基与基础工程施工。选项A错误，长度在10m以下的短桩，一般多在工厂预制，较长的桩，因不便于运输，通常就在打桩现场附近露天预制。 选项B错误，现场预制桩多用重叠法预制，重叠层数不宜超过4层。 选项C正确，钢筋混凝土预制桩应在混凝土达到设计强度的70%方可起吊；达到100%方可运输和打桩。 选项D错误，上层桩或邻近桩的灌注，应在下层桩或邻近桩混凝土达到设计强度等级的30%以后方可进行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]