[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906509,586,1,"单选题","地下水位以下或含水量超过（ ）的土，不宜采用土桩或灰土桩。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15％",false,{"key":16,"text":17,"correct":14},"B","20％",{"key":19,"text":20,"correct":21},"C","25％",true,{"key":23,"text":24,"correct":14},"D","30％","2020版教材P185 本题考查的是地基与基础工程施工。土桩主要适用于消除湿陷性黄土地基的湿陷性，灰土桩主要适用于提高人工填土地基的承载力。地下水位以下或含水量超过25%的土，不宜采用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]