[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906507":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906507,586,1,"单选题","目前多用于钢网架结构的吊装方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大跨度结构高空拼装法施工",true,{"key":16,"text":17,"correct":18},"B","大跨度结构整体吊装法施工",false,{"key":20,"text":21,"correct":18},"C","大跨度结构整体顶升法施工",{"key":23,"text":24,"correct":18},"D","大跨度结构滑移法施工","2020版教材P243 本题考查的是结构吊装工程施工。大跨度结构高空拼装法是先在设计位置搭设满堂或部分拼装支架，然后直接将网架杆件和节点吊运到拼装支架上进行拼装；或先将网架杆件和节点预拼成小拼单元，再将其吊运到拼装支架上进行整体拼装。此方法目前多用于钢网架结构的吊装。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]