[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906489,586,1,"单选题","下面关于预应力后张法的施工工艺，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","灌浆孔的间距，对预埋金属螺旋管不宜大于30m",true,{"key":16,"text":17,"correct":18},"B","孔道灌浆所用水泥浆拌和后至灌浆完毕的时间不宜超过35min",false,{"key":20,"text":21,"correct":18},"C","对后张法预应力梁，张拉时现浇结构混凝土的龄期不宜小于5d",{"key":23,"text":24,"correct":18},"D","张拉预应力筋时，设计无规定的，构件混凝土的强度不低于设计强度等级的50％","2020版教材P227 本题考查的是预应力混凝土工程施工。选项B错误，水泥浆拌和后至灌浆完毕的时间不宜超过30min。 选项C错误，对后张法预应力梁和板，现浇结构混凝土的龄期分别不宜小于7d和5d。 选项D错误，张拉预应力筋时，构件混凝土的强度应按设计规定，如设计无规定，则不低于设计的混凝土立方体抗压强度标准值的75%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]