[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906483":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906483,586,1,"单选题","预应力张拉时，下列不符合要求的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","长度为20米的有黏结预应力筋一端张拉",false,{"key":16,"text":17,"correct":14},"B","长度为30米的直线型有黏结预应力筋一端张拉",{"key":19,"text":20,"correct":21},"C","长度为45米的无黏结预应力筋一端张拉",true,{"key":23,"text":24,"correct":14},"D","长度为55米的无黏结预应力筋两端张拉","2020版教材P227 本题考查的是预应力的施加方法。预应力筋应根据设计和专项施工方案的要求采用一端或两端张拉。采用两端张拉时，宜两端同时张拉，也可一端先张拉，另一端补张拉。当设计无具体要求时，应符合下列规定：有黏结预应力筋长度不大于20m时可一端张拉，大于20m时宜两端张拉。预应力筋为直线形时，一端张拉的长度可延长至35m。无黏结预应力筋长度不大于40m时可一端张拉，大于40m时宜两端张拉。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]