[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906471":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906471,586,1,"单选题","打桩的顺序，以下说法不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基坑不大时，打桩应从中间开始分头向两边或四周进行",false,{"key":16,"text":17,"correct":14},"B","当桩基的设计标高不同时，应先深后浅",{"key":19,"text":20,"correct":14},"C","当桩的规格不同时，应先大后小，先长后短",{"key":22,"text":23,"correct":24},"D","当桩基的设计标高不同时，应先浅后深",true,"2020版教材P188 本题考查的是地基与基础工程施工。一般当基坑不大时，打桩应从中间分头向两边或四周进行；当基坑较大时，应将基坑分为数段，而后在各段范围内分别进行。打桩应避免自外向内，或从周边向中间进行。当桩基的设计标高不同时，打桩顺序易先深后浅；当桩的规格不同时，打桩顺序宜先大后小、先长后短。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]