[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906468":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906468,586,1,"单选题","装配整体式结构中，预制构件吊装就位后，应及时校准并（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取临时固定措施，每个预制构件的临时支撑不宜少于2道",true,{"key":16,"text":17,"correct":18},"B","采取临时固定措施，每个预制构件的临时支撑不宜少于3道",false,{"key":20,"text":21,"correct":18},"C","采取永久固定措施，每个预制构件的临时支撑不宜少于2道",{"key":23,"text":24,"correct":18},"D","采取永久固定措施，每个预制构件的临时支撑不宜少于3道","2020版教材P224 本题考查的是装配式混凝土施工。预制构件吊装就位后，应及时校准并采取临时固定措施，每个预制构件的临时支撑不宜少于2道，对预制柱、墙板构件的上部斜支撑，其支撑点距离板底的距离不宜小于构件高度的2\u002F3，且不应小于构件高度的1\u002F2。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]