[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},906463,586,1,"单选题","用推土机回填管沟，当无倒车余地时一般采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","沟槽推土法",false,{"key":16,"text":17,"correct":18},"B","斜角推土法",true,{"key":20,"text":21,"correct":14},"C","下坡推土法",{"key":23,"text":24,"correct":14},"D","分批集中，一次推土法","本题考查的是土石方工程施工技术。斜角推土法：将铲刀斜装在支架上，与推土机横轴在水平方向形成一定角度进行推土。一般在管沟回填且无倒车余地时可采用这种方法。 2020版教材P172-182",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]