[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906460":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906460,586,1,"单选题","在坚硬土层中，桥梁墩台基础施工优先采用的主要沉桩方法为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","射水沉桩",true,{"key":16,"text":17,"correct":18},"B","锤击沉桩",false,{"key":20,"text":21,"correct":18},"C","振动沉桩",{"key":23,"text":24,"correct":18},"D","静力压桩","本题考查的是桥梁下部结构施工。射水沉桩法的选择应视土质情况而异，在砂夹卵石层或坚硬土层中一般以射水为主，锤击或振动为辅；在亚黏土或黏土中，为避免降低承载力，一般以锤击或振动为主，以射水为辅，并应适当控制射水时间和水量，下沉空心桩；一般用单管内射水。 2020版教材P183-200",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]