[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906257":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906257,586,1,"单选题","有关桥面排水系统，下列叙述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","桥上纵坡不大于4％不小于0.3％",false,{"key":16,"text":17,"correct":14},"B","桥面横坡一般为3％～5％",{"key":19,"text":20,"correct":14},"C","纵坡大于2％时排水管截面积不宜小于100mm2／m2",{"key":22,"text":23,"correct":24},"D","纵坡大于2%时排水管截面积不宜小于60mm2／m2",true,"桥上纵坡机动车道不宜大于4%，非机动车道不宜大于2.5%；桥头引道机动车道纵坡不宜大于5%。高架桥桥面应设不小于0.3%的纵坡。桥面的横坡，一般采用1.5%~3.0%。当纵坡大于2%桥面设置排水管的截面积不宜小于60mm2\u002Fm2;当纵坡小于1%桥面设置排水管的截面积不宜小于100mm2\u002Fm2；南方潮湿地区和西北干燥地区可根据暴雨强度适当调整。 2020版教材P92-102",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]