[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906062":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906062,586,1,"单选题","根据《房屋建筑与装饰工程工程量计量规范》(GB50854--2013)，若开挖设计长为18m，宽为8m，深度为0.8 的土方工程，在清单中列项应为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","平整场地",false,{"key":16,"text":17,"correct":14},"B","挖沟槽",{"key":19,"text":20,"correct":21},"C","挖基坑",true,{"key":23,"text":24,"correct":14},"D","挖一般土方","本题考查的是土石方工程计算规则与方法。沟槽、基坑、一般土方的划分为：底宽 ≤7m 且底长>3 倍底宽为沟槽；底长≤3 倍底宽且底面积≤150 ㎡为基坑；超出上述范围则为一般土方。本题中底宽=8m＞7m，故不是沟槽，底长=18m＜3 倍底宽 8m，且 S=18*8=144 ㎡。故为挖基坑土方。@##",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]