[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906057,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013）规定，有关木结构工程量计算，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","木屋架的跨度应与墙或柱的支撑点间的距离计算",false,{"key":16,"text":17,"correct":14},"B","木屋架的马尾、折角工程量不予计算",{"key":19,"text":20,"correct":21},"C","钢木屋架钢拉杆、连接螺栓不单独列项计算",true,{"key":23,"text":24,"correct":14},"D","木柱区分不同规格以高度计算","本题考查的是木结构工程。屋架的跨度以上、下弦中心线两交点之间的距离计算，故 A 错误；带气楼的屋架和马尾、折角一级正交部分的半屋架，按相关屋架项目编码列项，故 B 错误；木柱、木梁按设计图示尺寸以体积计算，故 D 错误。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]