[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906025":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},906025,586,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），基坑支护的锚杆的工程量应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按设计图示尺寸以支护体积计算",false,{"key":16,"text":17,"correct":14},"B","按设计图示尺寸以支护面积计算",{"key":19,"text":20,"correct":21},"C","按设计图示尺寸以钻孔深度计算",true,{"key":23,"text":24,"correct":14},"D","按设计图示尺寸以质量计算","本题考查的是地基处理与边坡支护工程计算规则与方法。考查地基处理与边坡支护工程量计算。锚杆可以按孔深也可以按数量计量",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]