[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906022,586,1,"单选题","根据《建设工程工程量清单计价规范》，楼地面踢脚线工程量应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按设计图示中心线长度计算",false,{"key":16,"text":17,"correct":14},"B","按设计图示净长线长度计算",{"key":19,"text":20,"correct":14},"C","区分不同材料和规格以长度计算",{"key":22,"text":23,"correct":24},"D","按设计图示长度乘以高度以面积计算",true,"本题考查踢脚线的工程量计算。根据《建设工程工程量清单计价规范》(GB50854-2013)，工程量以平方米计算，按设计图示长度乘以高度以面积计算；以米计量，按延长米计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]