[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906020,586,1,"单选题","根据《建设工程工程量清单计价规范》。以下关于现浇混凝土工程量计算。正确的说法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有梁板柱高自柱基上表面至上层楼板上表面",true,{"key":16,"text":17,"correct":18},"B","无梁板柱高自柱基上表面至上层接板下表面",false,{"key":20,"text":21,"correct":18},"C","框架柱柱高自柱基上表面至上层楼板上表面",{"key":23,"text":24,"correct":18},"D","构造柱柱高自柱基上表面至顶层楼板下表面","本题考查现浇混凝土柱计算。选项 A 正确，有梁板的柱高，应自柱基上表面至上一层楼板上表面之间的高度计算；选项 B 错误，无梁板柱高，应自柱基上表面至柱帽下表面之间的高度；选项 C 错误，框架柱柱高应自柱基上表面至柱顶高度计算；选项 D 错误，构造柱按全高计算，嵌接墙体部分并入柱身体积。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]