[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906011,586,1,"单选题","单位工程中工程量计算顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平面图-剖面图-立面图",false,{"key":16,"text":17,"correct":14},"B","按消耗量定额的章、节、子目次序，由后向前，逐项对照",{"key":19,"text":20,"correct":14},"C","按工程量计算规范附录先后顺序，由后向前，逐项对照",{"key":22,"text":23,"correct":24},"D","按施工顺序计算，先施工先计算，后施工后计算",true,"本题考查单位工程计算顺序。①按图纸顺序计算，根据图纸排列的先后顺序，由建施到结施；每个专业图纸由前向后，按“先平面-再立面-再剖面-；先基本图-再详图”；②按消耗量定额的分部分项顺序计算；按消耗量定额的章、节、子目次序，由前向后，逐项对照，定额项与图纸设计内容能对上号时就计算；③按工程量计算规范顺序计算，按工程量计算规范附录先后顺序，由前向后，逐项对照计算；④按施工顺序计算，按施工顺序计算工程量，可以按先施工的先算，后施工的后算的方法进行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]