[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906008":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},906008,586,1,"单选题","单个分部分项工程计算顺序正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","从平面图的右上角开始，自右至左，然后再由上而下，最后转回到右上角为止",false,{"key":16,"text":17,"correct":14},"B","按“先竖后横、先上后下、先左后右”计算法",{"key":19,"text":20,"correct":14},"C","按照先基本图后详图的顺序计算",{"key":22,"text":23,"correct":24},"D","按照图纸上定位轴线编号计算",true,"本题考查单个分部分项工程计算顺序。单个分部分项工程计算顺序如下：（1）按照顺时针方向计算法，从平面图的左上角开始，自左至右，然后再由上而下，最后转回到左上角为止；（2）按“先横后竖、先上后下、先左后右”计算法；（3）按图纸分项编号顺序计算；（4）按照图纸上定位轴线编号计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]