[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-906003":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},906003,586,1,"单选题","《建设工程工程量清单计价规范》中，所列的分部分项清单项目的工程量主要是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计图示尺寸工程量",true,{"key":16,"text":17,"correct":18},"B","施工消耗工程量",false,{"key":20,"text":21,"correct":18},"C","不包括损耗的施工净量",{"key":23,"text":24,"correct":18},"D","考虑合理损耗的施工量","本题考查清单项目工程量计算规则清单项目工程量计算一般为施工图纸的净量，不考虑施工余量。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]