[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},905993,586,1,"单选题","采用沉井法施工，当沉井中心线与设计中心线不重合时，通常采用以下方法纠偏（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","通过起重机械吊挂调试",false,{"key":16,"text":17,"correct":14},"B","在沉井内注水调试",{"key":19,"text":20,"correct":21},"C","通过中心线两侧挖土调整",true,{"key":23,"text":24,"correct":14},"D","在沉井外侧卸土调整","本题考查地下工程沉井纠偏的方法。沉井纠偏有以下方法：当沉井中心线与设计中心线不重合时，可先在一侧挖土，使沉井倾斜，然后均匀挖土，使沉井沿倾斜方向下沉到沉井底面中心线接近设计中心线位置时再纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]