[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905984,586,1,"单选题","跨径100m 以下的桥梁施工时，为满足桥梁上下部结构平行作业和施工精度要求，优先选用的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","悬臂浇注法",false,{"key":16,"text":17,"correct":18},"B","悬臂拼装法",true,{"key":20,"text":21,"correct":14},"C","转体法",{"key":23,"text":24,"correct":14},"D","支架现浇法","本题考查的是桥梁上部结构的施工。悬臂浇筑施工简便，结构整体性好，施工中可不断调整位置，常在跨径大于 100m 的桥梁上选用；悬臂拼装法施工速度快，桥梁上下部结构可平行作业，但施工精度要求比较高，可在跨径 100m 以下的大桥中选用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]