[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905967,586,1,"单选题","预应力混凝土工程后张法施工中，模板拆除的要求是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","底模支架的拆除应按施工技术方案执行",true,{"key":16,"text":17,"correct":18},"B","底模在结构构件建立预应力前拆除",false,{"key":20,"text":21,"correct":18},"C","侧模板宜在预应力张拉后拆除",{"key":23,"text":24,"correct":18},"D","底模和侧模都应在结构构件建立预应力后拆除","本题考查模板拆除要求。对于后张法预应力混凝土构件，侧模板宜在预应力张拉前拆除；底模支架的拆除应按施工技术方案执行，当无具体要求时，不应在结构构件建立预应力前拆除。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]