[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},905850,586,1,"单选题","应避免因工程地质勘察不详而引起工程造价增加的情况是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地质对结构选型的影响",false,{"key":16,"text":17,"correct":14},"B","地质对基础选型的影响",{"key":19,"text":20,"correct":14},"C","设计阶段发现特殊不良地质条件",{"key":22,"text":23,"correct":24},"D","施工阶段发现特殊不良地质条件",true,"本题考查工程地质对工程造价的影响。题干中明确要求选择应避免引起工程造价增加的选项是哪个，选项 A 和选项 B 是工程地质对建筑结构的影响，不符合题意；选项 C 中设计阶段发现问题是直接影响工程造价；选项 D 施工中发现问题，会导致工程造价增加。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]