[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905772,586,1,"单选题","（2019年）根据《房屋建筑与装饰工程工程量计算规范》(GB508542013)，混凝土构件拆除清单工程量计算正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按拆除构件的虚方工程量计算，以“m3”计量",false,{"key":16,"text":17,"correct":18},"B","可按拆除部位的面积计算，“m2”计量",true,{"key":20,"text":21,"correct":14},"C","可按拆除构件的运输工程量计算，以“m3”计量",{"key":23,"text":24,"correct":14},"D","按拆除构件的质量计算，以“t”计量","混凝土构件拆除、钢筋混凝土构件拆除以\"m3\"计量，按拆除构件的混凝土体积计算；以 \"m2\" 计量，按拆除部位的面积计算，以 \"m\" 计量，按拆除部位的延长米计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]