[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905761,586,1,"单选题","（2019年）根据《房屋建筑与装饰工程量计算规范》（GB50854-2013），打预制钢筋混凝土土方桩清单工程量计算正常的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","打桩按打入实体长度（不包括桩尖）计算，以“m”计算",false,{"key":16,"text":17,"correct":18},"B","截桩头按设计桩截面乘以桩头长度计算，以“m3”计算",true,{"key":20,"text":21,"correct":14},"C","接桩按接头数量计算，以“个”计量",{"key":23,"text":24,"correct":14},"D","送桩按送入长度计算，以“m”计算","选项A错误，打桩长度包括桩尖。 选项B正确，截（凿）桩头，以\"m3\"计量，按设计桩截面乘以桩头长度以体积计算； 以\"根\"计量，按设计图示数量计算。 选项C、D错误，打桩的工程内容中包括了接桩和送桩，不需要单独列项，应在综合单价中考虑。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]