[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905759":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},905759,586,1,"单选题","（2019年）某建筑物砂土场地，设计开挖面积为20m×7m，自然地面标高为-0.2m，设计室外地坪高为-0.3m，设计开挖底面标高为-1.2m。根据《房屋建筑与装饰工程量计算规范》（GB50854-2013），土方工程清单工程量计算应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","执行挖一般土方项目，工程量为140m3",false,{"key":16,"text":17,"correct":14},"B","执行挖一般土方项目，工程量为126m3",{"key":19,"text":20,"correct":21},"C","执行挖基坑土方项目，工程量为140m3",true,{"key":23,"text":24,"correct":14},"D","执行挖基坑土方项目，工程量为126m3","沟槽、基坑、一般土方的划分为：底宽小于或等于7m ，底长大于3倍底宽为沟糟；底长小于或等于3倍底宽、底面积小于或等于150m2为基坑；超出上述范围则为一般土方。此题中为基坑土方，工程量为20*7*（1.2-0.2）=140m3。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]