[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905742,586,1,"单选题","(2017年)根据《房屋建筑与装饰工程计算规范》(GB50854-2013)，现浇混凝土工程量计算正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","雨篷与圈梁连接时其工程量以梁中心为分界线",false,{"key":16,"text":17,"correct":18},"B","阳台梁与圈梁连接部分并入圈梁工程量",true,{"key":20,"text":21,"correct":14},"C","挑檐板按设计图示水平投影面积计算",{"key":23,"text":24,"correct":14},"D","空心板按设计图示尺寸以体积计算,空心部分不予扣除","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]