[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905740":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},905740,586,1,"单选题","(2017年)根据《房屋建筑与装饰工程工程量计算规范》(GB50854-2013)，屋面防水及其他工程量计算正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","屋面卷材防水按设计示尺寸以面积计算，防水搭接及附加层用量按设计尺寸计算",false,{"key":16,"text":17,"correct":14},"B","屋面排水管设计未标注尺寸,考虑弯折处的增加以长度计算",{"key":19,"text":20,"correct":21},"C","屋面铁皮天沟按设计图示尺寸以展开面积计算",true,{"key":23,"text":24,"correct":14},"D","屋面变形缝按设计尺寸以铺设面积计算","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]