[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},905738,586,1,"单选题","(2017年)根据《房屋建筑与装饰工程工程量计算规范》（GB\u002FT50854-2013），某建筑物场地土方工程，设计基础长27m，宽为8m，周边开挖深度均为2m，实际开挖后场内堆土量为570m3，则土方工程量为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平整场地216m3",false,{"key":16,"text":17,"correct":14},"B","沟槽土方655m3",{"key":19,"text":20,"correct":14},"C","基坑土方528m3",{"key":22,"text":23,"correct":24},"D","一般土方438m3",true,"首先判断属于一般土方项目。其次确定工程量：570*0.77=439 或570\u002F1.30=438。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]