[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},905728,586,1,"单选题","(2015年)根据《房屋建筑与装饰工程工程量计算规范》(GB50854-2013)规定，关于地基处理工程量计算正确的为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","振冲桩（填料）按设计图示处理范围以面积计算",false,{"key":16,"text":17,"correct":14},"B","砂石桩按设计图示尺寸以桩长（不包括桩尖）计算",{"key":19,"text":20,"correct":14},"C","水泥粉煤灰碎石桩按设计图示尺寸以体积计算",{"key":22,"text":23,"correct":24},"D","深层搅拌桩按设计图示尺寸以桩长计算",true,"振冲桩（填料）以米计量，按设计图示尺寸以桩长计算；砂石桩以米计量，按设计图示尺寸以桩长（包括桩尖）计算；水泥粉煤灰碎石桩、劳实水泥土桩、石灰桩、灰土（土）挤密桩的工程量均以米计量，按设计图示尺寸以桩长（包括桩尖）计算；深层搅拌桩、粉喷桩、柱锤冲扩桩的工程量以米计量，按设计图示尺寸以桩长计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]