[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905700":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905700,586,1,"单选题","(2015年)根据《房屋建筑与装饰工程工程量计算规范》(GB50854-2013)规定，关于石方的项目列项或工程量计算正确的为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","山坡凿石按一般石方列项",true,{"key":16,"text":17,"correct":18},"B","考虑石方运输，石方体积需折算为虚方体积计算",false,{"key":20,"text":21,"correct":18},"C","管沟石方均按一般石方列项",{"key":23,"text":24,"correct":18},"D","基坑底面积超过120m2的按一般石方列项","(1)厚度＞±300mm的竖向布置挖石或山坡凿石应按挖一般石方项目编码列项。P369：石方体积应按挖掘前的天然密实体积计算，故选项B错误。P372：管沟石方，按设计图示以管道中心线长度计算；按设计图示截面积乘以长度计算，故选项C错误。P371：沟槽、基坑、一般石方的划分为：底宽≤7m且底长＞3倍底宽为沟槽；底长≤3倍底宽且底面积≤150m2为基坑；超出上述范围：则为一般石方，故选项D错误。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]