[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},905699,586,1,"单选题","(2015年)某管沟工程，设计管底垫层宽度为2000mm，开挖深度为2.00m，管径为1200mm，工作面宽为400mm，管道中心线长为180m，管沟土方工程量计算正确的为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","432m3",false,{"key":16,"text":17,"correct":14},"B","576m3",{"key":19,"text":20,"correct":21},"C","720m3",true,{"key":23,"text":24,"correct":14},"D","1008m3","按设计图示以管道中心线长度计算，或按设计图示管底垫层面积乘以挖土深度以体积 计算。无管底垫层按管外径的水平投影面积乘以挖土深度计算。不扣除各类井的长度，井的土方并入。故管沟土方工程量=2×2×180=720(m3)。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]