[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905686,586,1,"单选题","(2013年)据《房屋建筑与装饰工程工程量计算规范》(GB50854-2013)，关于基坑与边坡支护工程量计算的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地下连续墙按设计图示尺寸以体积计算",true,{"key":16,"text":17,"correct":18},"B","咬合灌注桩按设计图示尺寸以体积计算",false,{"key":20,"text":21,"correct":18},"C","喷射混凝土按设计图示以体积计算",{"key":23,"text":24,"correct":18},"D","预制钢筋混凝土板桩按照设计图示尺寸以体积计算","选项A，地下连续墙按设计图示墙中心线长乘以厚度乘以槽深以体积计算，单位。选项B，咬合灌注桩按设计图示尺寸以桩长计算；或按设计图示数量计算。选项C，喷射混凝土（水泥砂浆）按设计图示尺寸以面积计算。选项D，预制混凝土板按设计图示尺寸以体积计算；预制钢筋混凝土方桩、预制钢筋混凝土管桩按设计图示尺寸以桩长（包括、桩尖）计算，或按设计图示截面积乘以桩长（包括桩尖）以实体积计算，或按设计图示数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]