[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905677":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905677,586,1,"单选题","（2019年）工程量清单特征描述主要说明( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施项目的质量安全要求",false,{"key":16,"text":17,"correct":18},"B","确定综合单价需考虑的问题",true,{"key":20,"text":21,"correct":14},"C","清单项目的计算规则",{"key":23,"text":24,"correct":14},"D","分部分项项目和措施项目的区别","项目特征体现的是对清单项目的质量要求，是确定一个清单项目综合单价不可缺少的重要依据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]