[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},905676,586,1,"单选题","(2018年)在同一合同段的工程量清单中多个单位工程中具有相同项目特征的项目编码和计量单位时（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目编码不一致，计量单位不一致",false,{"key":16,"text":17,"correct":14},"B","项目编码一致，计量单位一致",{"key":19,"text":20,"correct":21},"C","项目编码不一致，计量单位一致",true,{"key":23,"text":24,"correct":14},"D","项目编码一致，计量单位不一致","",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]