[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},905669,586,1,"单选题","(2013年)根据《房屋建筑与装饰工程工程量计算规范》(GB50854-2013)，编制工程量清单补充项目时，编制人应报奋案的单位是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","企业技术管理部门",false,{"key":16,"text":17,"correct":14},"B","工程所在地造价管理部门",{"key":19,"text":20,"correct":21},"C","省级或行业工程造价管理机构",true,{"key":23,"text":24,"correct":14},"D","住房和城乡建设部标准定额研究所","在编制工程量清单时，当出现规范附录中未包括的清单项目时，编制人应作补充，并报省级或行业工程造价管理机构备案，省级或行业工程造价管理机构应汇总报住房和城乡建设部标准定额研究所。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]