[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905662,586,1,"单选题","（2019年）关于深基坑土方开挖采用冻结排桩法支护技术，下列说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","冻结管应置于排桩外侧",true,{"key":16,"text":17,"correct":18},"B","卸压孔应置于冻结管和排桩之间",false,{"key":20,"text":21,"correct":18},"C","冻结墙的主要作用是支撑土体",{"key":23,"text":24,"correct":18},"D","排桩的主要作用是隔水","冻结排桩法施工 ，即在基坑开挖之前，根据基坑开挖深度，利用钻孔灌注桩技术沿基坑四周超前施工一排灌注桩，并用现浇钢筋混凝土梁把排桩顶端固定在一起使排桩形成支撑结构体系，并在排桩外侧按设计要求施做一排冻结孔，同时在冻结孔外侧据其中心一定位置处插花布设多个卸压孔；然后利用人工冻结技术形成冻土墙隔水帷幕，与超前施做的排桩支撑结构体系一道形成一临时支护结构，在此支护结构的保护下进行基坑开挖，并随着开挖深度的增加支设内支撑以保证支护结构的稳定，当开挖至设计标高时，浇筑垫层混凝土。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]