[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905654,586,1,"单选题","(2013年)地下工程的早强水泥砂浆锚杆用树脂药包的，正常温度下需要搅拌的时间为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30s",true,{"key":16,"text":17,"correct":18},"B","45～60s",false,{"key":20,"text":21,"correct":18},"C","3min",{"key":23,"text":24,"correct":18},"D","5min","采用树脂药包时， 还应注意：搅拌时间应根据现场气温决定，20℃时固化时间为5min；温度下降5℃时固化时间约会延长一倍， 即15℃时为 10min; 10℃时为 20min。 因此， 地下工程在正常温度下， 搅拌时间约为30s， 当温度在10℃以下时， 搅拌时间可适当延长为 45～60s。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]