[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},905634,586,1,"单选题","(2013年)填筑路堤前是否需要进行基底处理不取决于()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地面横坡陡缓",false,{"key":16,"text":17,"correct":14},"B","基地土层松实",{"key":19,"text":20,"correct":14},"C","填方高度大小",{"key":22,"text":23,"correct":24},"D","填料土体性质",true,"为使两者紧密结合以保证填筑后的路堤不至于产生沿基底的滑动和过大变形，填筑路堤前，应根据基底的土质、水文、坡度、植被和填土高度采取一定措施对基底进行处理。选项A、B、C均为决定是否进行基底处理时应考虑的因素。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]