[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905623,586,1,"单选题","（2019年）关于装配式混凝土施工，下列说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水平运输梁柱构件时，叠放不宜超过3层",true,{"key":16,"text":17,"correct":18},"B","水平运输板类构件时，叠放不宜超过7层",false,{"key":20,"text":21,"correct":18},"C","钢筋套筒连接灌浆施工时，环境温度不得低于10℃",{"key":23,"text":24,"correct":18},"D","钢筋套筒连接施工时，连接钢筋偏离孔洞中心线不宜超过10mm","选项A正确，B错误，水平运输时，预制梁、柱构件叠放不宜超过3层，板类构件叠放不宜超过6层。 选项C错误，钢筋套筒灌浆施工时，环境温度不应低于5℃；当连接部位养护温度低于10℃时，应采取加热保温措施。 选项D错误，连接钢筋偏离套筒或孔洞中心线不宜超过5mm。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]