[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905602,586,1,"单选题","(2017年)钢筋混凝土预制桩锤击沉桩法施工,通常采用( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","轻锤低击的打桩方式",false,{"key":16,"text":17,"correct":18},"B","重锤低击的打桩方式",true,{"key":20,"text":21,"correct":14},"C","先四周后中间的打桩顺序",{"key":23,"text":24,"correct":14},"D","先打短桩后打长桩","桩锤的选择应先根据施工条件确定桩锤的类型，然后再决定锤重。要求锤重应有足够的冲击能，锤重应大于等于桩重。这是因为在施工中，宜采用\"重锤低击\"。一般当基坑不大时，打桩应从中间分头向两边或四周进行；当基坑较大时，应将基坑分为数段，而后在隔断范围内分别进行。打桩应避免自外向内，或从周边向中间进行。当桩基的设计标高不同时，打桩顺序易先深后浅；当桩的规格不同时，打桩顺序宜先大后小、先长后短。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]