[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905596,586,1,"单选题","(2016年)关于钢筋混凝土预制桩施工，说法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基坑较大时，打桩宜从周边向中间进行",false,{"key":16,"text":17,"correct":18},"B","打桩宜采用重锤低击",true,{"key":20,"text":21,"correct":14},"C","钢筋混凝土预制桩堆放层数不超过2层",{"key":23,"text":24,"correct":14},"D","桩体混凝土强度达到设计强度的70%方可运输","选项A错误，基坑较大时，应将基坑分为数段，而后在各段范围内分别进行；选项B正确，锤击沉桩是预制桩最常用的沉桩方法；选项C错误，桩堆放时，地面必须平整、坚实，不得产生不均匀沉陷。桩堆放时应设置垫木，垫木的位置与吊点位置相同，各层垫木应上下对齐，堆放层数不宜超过4层，不同规格的桩应分别堆放；选项D错误，钢筋混凝土预制桩应在混凝土达到设计强度的70%方可起吊，达到100%方可运输和打桩。如提前吊运，应采取措施并经验算合格后方可进行。桩在起吊和搬运时，吊点应符合设计要求，满足吊桩弯矩最小的原则。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]