[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905590,586,1,"单选题","(2013年)现场采用重叠法预制钢筋混凝土桩时，上层桩的浇注应等到下层桩混凝土强度达到设计强度等级的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30%",true,{"key":16,"text":17,"correct":18},"B","60%",false,{"key":20,"text":21,"correct":18},"C","70%",{"key":23,"text":24,"correct":18},"D","100%","现场预制桩多用重叠法预制，重叠层数不宜超过4层，层与层之间应涂刷隔离剂，上层桩或邻近桩的灌注，应在下沉桩或邻近桩混凝土达到设计强度等级的30%以后方可进行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]