[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},905582,586,1,"单选题","(2015年)预应力混凝土构件先张法施工工艺流程正确的为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安骨架、钢筋→张拉→安底、侧模→浇灌→养护→拆模→放张",false,{"key":16,"text":17,"correct":18},"B","安底模、骨架、钢筋→张拉→支侧模→浇灌→养护→拆模→放张",true,{"key":20,"text":21,"correct":14},"C","安骨架一安钢筋→安底、侧模→浇灌→张拉→养护→放张→拆模",{"key":23,"text":24,"correct":14},"D","安底模、侧模→安钢筋→张拉→浇灌→养护→放张→拆模","先张法工艺流程：按底模、骨架、钢筋→张拉→支侧模→浇灌→养护→拆模→张放。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]