[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},905428,586,1,"单选题","(2009年)应避免因工程地质勘察不详而引起工程造价增加的情况是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","地质对结构选型的影响",false,{"key":16,"text":17,"correct":14},"B","地质对基础选型的影响",{"key":19,"text":20,"correct":14},"C","设计阶段发现特殊不良地质条件",{"key":22,"text":23,"correct":24},"D","施工阶段发现特殊不良地质条件",true,"工程地质勘查作为一项基础性工作， 对工程造价的影响可归结为三个方面；一是选择工程地质条件有利的路线，对工程造价起着决定作用；二是勘察资料的准确性直接影响工程价；三是由于对特殊不良工程地质问题认识不足导致的工程造价增加。通常，往往存在着因施工过程才发现特殊不良地质的现象。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]