[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905387,586,1,"单选题","(2018年)隧道选线与断层走线平行，应优先考虑()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","避开与其破碎带接触",true,{"key":16,"text":17,"correct":18},"B","横穿其破碎带",false,{"key":20,"text":21,"correct":18},"C","灌浆加固断层破碎带",{"key":23,"text":24,"correct":18},"D","清除断层破碎带","当隧道轴线与断层走向平行时，应尽量避免与断层破碎带接触。隧道横穿断层时，虽然只是个别段落受断层影响，但因地质及水文地质条件不良，必须预先考虑措施,保证施工安全。特别当岩层破碎带规模很大，或者穿越断层带时，会使施工十分困难，在确定隧道平面位置时间，应尽量设法避开。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]