[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},905386,586,1,"单选题","(2018年)隧道选线时，应优选布置在（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","褶皱两侧",true,{"key":16,"text":17,"correct":18},"B","向斜核部",false,{"key":20,"text":21,"correct":18},"C","背斜核部",{"key":23,"text":24,"correct":18},"D","断层带","在向斜核部不宜修建地下工程。从理论而言,背斜核部较向斜优越,但实际上由于背斜核部外缘受拉伸处于张力带,内缘受挤压.加上风化作用,岩层往往很破碎。因此,在布置地下工程时,原则上应避开褶皱核部。若必须在褶皱岩层地段修建地下工程,可以将地下工程放在褶皱的两侧。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（土建）","建筑工程",0]